# Create and apply a plan

> Create a supply plan from a demand, review the proposed purchase orders and runs, refresh it against live supply, and commit the draft package to ION.

In ION, go to **Supply Chain > Autoplan**. The list page shows every plan as a card with its status, phase, and percent generated and fulfilled. Select **Show archived** to include archived plans.

## Create a plan

1. Click **New Plan**.
2. Select the **Top-level part**, the finished assembly or part you need to deliver. Autoplan plans from its released BOM.
3. Enter the **Demand quantity** as a whole number, and optionally a **Due date**. Autoplan uses the due date to calculate order-by dates, slack, and critical-path risk.
4. Click **Next: Assumptions** and review the planning and purchasing assumptions the plan starts from. Any field you leave blank keeps your organization's defaults. See [Edit part policies in a plan](/manage-supply-chain/planning/part-policies) for what each field does.
5. Click **Create Plan**.

The plan opens and shows **Staging the plan** while Autoplan resolves the bill of materials, which usually takes a few seconds. If staging fails, the plan shows the reason and a **Retry** button.

## Review the staged plan and run it

Once the plan shows the **Staged** badge, review it before running:

* The **Overview** tab holds the **Demand** card, the **Planning assumptions** and **Per-part policy** panels, and the **BOM & order policy** card. In the **Demand** card, adjust each line's **Quantity**, **Due date**, and **Priority**. In **BOM & order policy**, set the **Allocation strategy** (**FIFO**, **LIFO**, or **Nearest due date**) and the **Safety buffer quantity**. Edits save when you leave the field.
* The **Components** tab lists every resolved component with its **Make / Buy** classification, sourcing, lead time, required quantity, on-hand quantity, and shortfall. Correct a part's **Make / Buy** value here if it is wrong; it decides whether Autoplan proposes a purchase order or a run for the part.

When the inputs look right, click **Run Autoplan**. The status shows **Running** while the engine computes, then the plan opens in the full workspace with results.

## Review the results

The plan header shows the status pill, a schedule-health pill (**On track**, **At risk**, or **Late**), and a supply-coverage summary such as "Supply covered for 4 of 10 components (6 short)". If the plan has multiple phases, use the **Phase** buttons to focus one planning pass at a time. **Download CSV** exports the visible plan lines.

Four views break down the proposals:

* **Worklist** is the action view. Shortfall lines are grouped into time-phased buckets by order-by date: **Overdue**, **Order now (≤7d)**, **Soon (≤30d)**, **Later (≤90d)**, and **Future (>90d)**, each split into buy and make tables.
* **Build tree** shows the plan as the build hierarchy, including parts already covered by inventory, with a coverage badge and a **Clear to build** read per assembly.
* **Supply readiness** leads with attention items, the rows that still threaten the plan, plus the purchase orders and manufacturing runs already linked to it.
* **Timeline** is a Gantt view of the plan schedule. It is marked **Preview**.

## Stage the proposals

Staging collects the proposals you accept into an editable draft package. Nothing is created in ION yet.

1. In the **Worklist**, select rows in a bucket and click **Stage POs** or **Schedule runs**, or click **Stage all in this bucket**. In **Supply readiness**, select attention rows and click **Stage selected**. Buy parts route to draft purchase orders and make parts to draft runs automatically.
2. Open the **Staging** tab. Its badge shows how many lines are staged.
3. Review the draft purchase orders, grouped by supplier. Edit each line's **Quantity**, **Supplier**, **Need date**, and **Unit cost**, or remove lines and groups. Every line needs a supplier before you can commit.
4. Review the draft runs in the production run batch, edit their quantities and due dates, and rename the batch if you want.

## Refresh the plan

Click **Refresh** in the plan header whenever your supply chain or shop floor changes. Refresh re-pulls live supply from ION and recomputes the same plan in place; the plan ID does not change. The "Supply as of" timestamp in the header shows when the plan last refreshed.

## Apply the plan

Committing the staged package is what creates real records in ION:

1. On the **Staging** tab, check the package summary and the **Total estimated spend**.
2. Click **Execute / Commit to ION**.
3. Confirm with **Commit to ION**. ION creates the purchase orders in draft status, so nothing is issued to suppliers, and creates the runs as a batch.

The **Committed to ION** section lists everything created, with links to each purchase order and run. If the purchase orders succeed but the runs fail, the button changes to **Retry runs only** so a retry never duplicates the purchase orders.

## Archive a plan

When a plan is done or no longer needed, click **Archive** in the plan header. Choose **Release eligible allocations** to return unconsumed inventory allocations to available supply (recommended), or **Keep allocations assigned** to keep supply reserved to the archived plan. Archived plans stay readable, and their linked purchase orders and runs remain as history.

## Related

* [Planning overview](/manage-supply-chain/planning)
* [Edit part policies in a plan](/manage-supply-chain/planning/part-policies)
* [Configure demand settings](/administration/supply-chain-settings/configure-demand-settings)
* [Create a purchase order](/manage-supply-chain/purchasing/create-a-purchase-order)